Assessment Year | 2021 |
---|---|
Principal Product | Mixing and blending equipment |
NAICS | 333249: Other Industrial Machinery Manufacturing |
SIC | 3559: Special Industry Machinery, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 95 |
Plant Area |
140,000
ft2
|
Annual Production | 50,000
pieces
|
Production Hrs. Annual | 4,252
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $46,667 | 1,054,900 |
kWh
|
$0.044 | |
Electricity Demand | $42,800 | 4,448 |
kW-mo/yr
|
$9.62 | |
Electricity Fees | $7,381 | - |
|
- | |
Natural Gas | $15,558 | 3,302 |
MMBtu
|
$4.71 | |
Waste Disposal Costs | |||||
Water Usage | $25,469 | 3,088 |
Tgal
|
$8.25 | |
TOTAL YEARLY COSTS | $137,875 | ||||
RECOMMENDED SAVINGS* | $60,040 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $45,620 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.8121: Apply for tax-free status for energy purchases | $42,750 | $3,000 | - | - | $7,381 | $1,169 | - | $34,200 | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $11,430 | $11,910 |
$5,130
116,000
kWh
|
$6,300
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,750 | $1,150 |
$1,230
28,000
kWh
|
$1,520
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.4157: Establish a predictive maintenance program | $1,250 | $4,570 |
$120
2,790
kWh
|
- | - | - | $1,130 | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,510 | $15 |
$680
15,330
kWh
|
$830
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.4314: Use synthetic lubricant | $230 | $150 |
$100
2,210
kWh
|
$130
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.6218: Turn off equipment when not in use | $120 | - |
$120
2,705
kWh
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $60,040 | $20,795 |
$7,380
167,035
kWh
|
$8,780
-
kW-mo/yr
|
$7,381 | $1,169 | $1,130 | $34,200 | ||
TOTAL IMPLEMENTED | $45,620 | $4,150 |
$1,350
30,705
kWh
|
$1,520
-
kW-mo/yr
|
$7,381 | $1,169 | - | $34,200 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs