ITAC Assessment: AM0815
ITAC logo
ITAC Assessment: AM0815
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2021
Principal Product wastewater treatment
NAICS 221320: Sewage Treatment Facilities
SIC 4952: Sewerage Systems
Sales Range less than $500
k
# of Employees 2
Plant Area 100,000
ft2
Annual Production 912,500
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $45,294 1,237,463
kWh
Electricity Demand $33,741 3,085
kW-mo/yr
Electricity Fees $984 -
TOTAL YEARLY COSTS $80,019
RECOMMENDED SAVINGS* $4,660 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $520

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Ancillary Material Cost Savings
01 2.4157: Establish a predictive maintenance program $1,330 $4,570 $330
8,780
kWh
- $1,000
02 2.3212: Optimize plant power factor $2,600 $3,770 - $2,600
-
kW-mo/yr
-
03 2.4314: Use synthetic lubricant $520 $200 $320
8,720
kWh
$200
-
kW-mo/yr
-
04 2.7135: Install occupancy sensors $210 $200 $210
5,610
kWh
- -
TOTAL RECOMMENDED $4,660 $8,740 $860
23,110
kWh
$2,800
-
kW-mo/yr
$1,000
TOTAL IMPLEMENTED $520 $200 $320
8,720
kWh
$200
-
kW-mo/yr
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs