Assessment Year | 2021 |
---|---|
Principal Product | Lighting products |
NAICS | 335122: Commercial, Industrial, and Institutional Electric Lighting Fixture Manufacturing |
SIC | 3646: Commercial, Industrial, and Institutional Electric Lighting Fixtures |
Sales Range | $10 M to 50M |
# of Employees | 75 |
Plant Area |
220,000
ft2
|
Annual Production | 100,000
pieces
|
Production Hrs. Annual | 2,117
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $79,805 | 2,326,200 |
kWh
|
$0.034 |
Electricity Demand | $66,317 | 8,354 |
kW-mo/yr
|
$7.94 |
Electricity Fees | $18,788 | - |
|
- |
Natural Gas | $33,920 | 5,093 |
MMBtu
|
$6.66 |
TOTAL YEARLY COSTS | $198,830 | |||
RECOMMENDED SAVINGS* | $92,630 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $86,170 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.8121: Apply for tax-free status for energy purchases | $74,300 | $7,400 | - | - | $14,860 | - | $59,440 | |
02 | 2.6218: Turn off equipment when not in use | $7,570 | $2,000 |
$5,230
153,700
kWh
|
$2,340
-
kW-mo/yr
|
- | - | - | |
03 | 2.3212: Optimize plant power factor | $6,460 | $9,830 | - |
$6,460
-
kW-mo/yr
|
- | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,540 | $1,000 |
$680
19,980
kWh
|
$860
-
kW-mo/yr
|
- | - | - | |
05 | 2.4157: Establish a predictive maintenance program | $1,470 | $4,340 |
$150
4,320
kWh
|
$190
-
kW-mo/yr
|
- | $1,130 | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $500 | $25 |
$220
6,470
kWh
|
$280
-
kW-mo/yr
|
- | - | - | |
07 | 2.8123: Pay utility bills on time | $490 | - | - | - | - | $490 | - | |
08 | 2.4314: Use synthetic lubricant | $300 | $200 |
$130
3,930
kWh
|
$170
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $92,630 | $24,795 |
$6,410
188,400
kWh
|
$10,300
-
kW-mo/yr
|
$14,860 | $1,620 | $59,440 | ||
TOTAL IMPLEMENTED | $86,170 | $14,965 |
$6,410
188,400
kWh
|
$3,840
-
kW-mo/yr
|
$14,860 | $1,620 | $59,440 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs