ITAC Assessment: AM0614
ITAC logo
ITAC Assessment: AM0614
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2012
Principal Product Steel doors
NAICS 332321: Metal Window and Door Manufacturing
SIC 3442: Metal Doors, Sash, Frames, Molding, and Trim Manufacturing
Sales Range $10
M
to 50
M
# of Employees 62
Plant Area 60,000
ft2
Annual Production 500,000
pieces
Production Hrs. Annual 4,000
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $144,027 2,422,610
kWh
Electricity Demand $70,565 10,352
kW-mo/yr
Electricity Fees $10,975 -
Natural Gas $48,172 9,790
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $72,220 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $71,690

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
01 2.3212: Optimize plant power factor $12,400 $24,400 - $12,400
-
kW-mo/yr
- - - -
02 2.8121: Apply for tax-free status for energy purchases $51,500 $1,500 - - $10,300 - - $41,200
03 2.4231: Reduce the pressure of compressed air to the minimum required $3,300 $15 $2,500
50,000
kWh
$800
-
kW-mo/yr
- - - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,800 $700 $1,300
25,200
kWh
$500
-
kW-mo/yr
- - - -
05 2.7124: Make a practice of turning off lights when not needed $1,500 $5,370 $1,010
21,100
kWh
$490
-
kW-mo/yr
- - - -
06 2.4226: Use / purchase optimum sized compressor $700 $780 $700
13,700
kWh
- - - - -
07 2.4314: Use synthetic lubricant $490 - $390
7,744
kWh
$100
-
kW-mo/yr
- - - -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $500 $280 $85
1,692
kWh
$15
-
kW-mo/yr
- - $400 -
09 2.2136: Install / repair insulation on steam lines $30 $630 - - - $30
-
MMBtu
- -
TOTAL RECOMMENDED $72,220 $33,675 $5,985
119,436
kWh
$14,305
-
kW-mo/yr
$10,300 $30
-
MMBtu
$400 $41,200
TOTAL IMPLEMENTED $71,690 $32,765 $5,900
117,744
kWh
$14,290
-
kW-mo/yr
$10,300 - - $41,200
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs