ITAC Assessment: AS0599
ITAC logo
ITAC Assessment: AS0599
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Sand
NAICS 212321: Construction Sand and Gravel Mining
SIC 1442: Construction Sand and Gravel
Sales Range $10
M
to 50
M
# of Employees 80
Plant Area 400,000
ft2
Annual Production 8,760,000
ton
Production Hrs. Annual 8,712
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,901,578 9,664,836
kWh
Electricity Demand $84,871 19,416
kW-mo/yr
Electricity Fees $104,902 -
LPG $1,565,908 131,557
MMBtu
TOTAL YEARLY COSTS $3,657,259
RECOMMENDED SAVINGS* $1,715,848 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings LPG Savings Fuel Oil #1 Savings Personnel Changes Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
01 2.1331: Burn a less expensive grade of fuel $625,275 $321,478 - - $(-940,633.0)
-
MMBtu
$1,565,908
-
MMBtu
- - - -
02 2.5194: Redesign process $778,933 $500,000 $96,932
492,660
kWh
$1,483
-
kW-mo/yr
- $430,518
-
MMBtu
- - - $250,000
03 4.651: Install back-up equipment $297,917 $1,360,000 - - - - $(-81,299.0)
-
MMBtu
$(-4,784.0) - $384,000
04 2.7142: Utilize higher efficiency lamps and/or ballasts $13,723 $5,870 $11,400
57,935
kWh
$168
-
kW-mo/yr
- - - - $2,155 -
TOTAL RECOMMENDED $1,715,848 $2,187,348 $108,332
550,595
kWh
$1,651
-
kW-mo/yr
$(-940,633.0)
-
MMBtu
$1,996,426
-
MMBtu
$(-81,299.0)
-
MMBtu
$(-4,784.0) $2,155 $634,000
TOTAL IMPLEMENTED - - - - - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs