| Assessment Year | 2025 |
|---|---|
| Principal Product | Sand |
| NAICS | 212321: Construction Sand and Gravel Mining |
| SIC | 1442: Construction Sand and Gravel |
| Sales Range | $10 M to 50M |
| # of Employees | 80 |
| Plant Area |
400,000
ft2
|
| Annual Production | 8,760,000
ton
|
| Production Hrs. Annual | 8,712
hrs
|
| Location (State) | Arizona |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,901,578 | 9,664,836 |
kWh
|
$0.20 |
| Electricity Demand | $84,871 | 19,416 |
kW-mo/yr
|
$4.37 |
| Electricity Fees | $104,902 | - |
|
- |
| LPG | $1,565,908 | 131,557 |
MMBtu
|
$11.90 |
| TOTAL YEARLY COSTS | $3,657,259 | |||
| RECOMMENDED SAVINGS* | $1,715,848 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | Fuel Oil #1 Savings | Personnel Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.1331: Burn a less expensive grade of fuel | $625,275 | $321,478 | - | - |
$(-940,633.0)
-
MMBtu
|
$1,565,908
-
MMBtu
|
- | - | - | - | |
| 02 | 2.5194: Redesign process | $778,933 | $500,000 |
$96,932
492,660
kWh
|
$1,483
-
kW-mo/yr
|
- |
$430,518
-
MMBtu
|
- | - | - | $250,000 | |
| 03 | 4.651: Install back-up equipment | $297,917 | $1,360,000 | - | - | - | - |
$(-81,299.0)
-
MMBtu
|
$(-4,784.0) | - | $384,000 | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13,723 | $5,870 |
$11,400
57,935
kWh
|
$168
-
kW-mo/yr
|
- | - | - | - | $2,155 | - | |
| TOTAL RECOMMENDED | $1,715,848 | $2,187,348 |
$108,332
550,595
kWh
|
$1,651
-
kW-mo/yr
|
$(-940,633.0)
-
MMBtu
|
$1,996,426
-
MMBtu
|
$(-81,299.0)
-
MMBtu
|
$(-4,784.0) | $2,155 | $634,000 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs