ITAC Assessment: AM0591
ITAC logo
ITAC Assessment: AM0591
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2011
Principal Product Phenolic resins, formaldehyde, wax
NAICS 325520: Adhesive Manufacturing
SIC 2891: Adhesives and Sealants
Sales Range $50
M
to 100
M
# of Employees 40
Plant Area 100,000
ft2
Annual Production 95,750
ton
Production Hrs. Annual 7,200
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $191,599 4,215,600
kWh
Electricity Demand $64,921 8,208
kW-mo/yr
Natural Gas $235,550 46,600
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $219,355 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $31,455

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Ancillary Material Cost Savings
01 3.4151: Minimize water usage $141,000 $80,000 - - $(-31,800.0)
-
MMBtu
$172,800
-
Tgal
-
02 2.2511: Insulate bare equipment $42,800 $13,800 $42,800
778,900
kWh
- - - -
03 2.3212: Optimize plant power factor $10,060 $15,900 - $10,060
-
kW-mo/yr
- - -
04 2.2135: Repair and eliminate steam leaks $9,540 $5,000 - - $9,540
-
MMBtu
- -
05 2.2113: Repair or replace steam traps $5,270 $1,300 - - $5,270
-
MMBtu
- -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $2,275 $4,290 $1,800
32,700
kWh
$365
-
kW-mo/yr
- - $110
07 2.2511: Insulate bare equipment $2,200 $950 - - $2,200
-
MMBtu
- -
08 2.2511: Insulate bare equipment $2,130 $950 $2,130
37,850
kWh
- - - -
09 2.7124: Make a practice of turning off lights when not needed $1,800 $325 $1,300
23,700
kWh
$500
-
kW-mo/yr
- - -
10 2.4231: Reduce the pressure of compressed air to the minimum required $1,500 - $1,250
22,700
kWh
$250
-
kW-mo/yr
- - -
11 2.7145: Install skylights $470 - $470
8,600
kWh
- - - -
12 2.7444: Close holes and openings in building such as broken windows $310 $170 $310
5,680
kWh
- - - -
TOTAL RECOMMENDED $219,355 $122,685 $50,060
910,130
kWh
$11,175
-
kW-mo/yr
$(-14,790.0)
-
MMBtu
$172,800
-
Tgal
$110
TOTAL IMPLEMENTED $31,455 $27,935 $3,410
62,080
kWh
$10,925
-
kW-mo/yr
$17,010
-
MMBtu
- $110
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs