ITAC Assessment: AM0534
ITAC logo
ITAC Assessment: AM0534
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2007
Principal Product Power generation turbines
NAICS 335312: Motor and Generator Manufacturing
SIC 3621: Motors and Generators
Sales Range greater than $500
M
# of Employees 536
Plant Area 250,000
ft2
Annual Production 211
pieces
Production Hrs. Annual 4,816
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $991,769 14,369,008
kWh
Electricity Demand $283,235 40,896
kW-mo/yr
Electricity Fees $2,574 -
Natural Gas $1,998,421 280,925
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $36,100 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $34,950

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $14,500 $1,500 $11,800
157,000
kWh
$2,700
-
kW-mo/yr
02 2.4231: Reduce the pressure of compressed air to the minimum required $7,500 $20 $6,100
81,700
kWh
$1,400
-
kW-mo/yr
03 2.7442: Keep doors and windows shut when not on use $7,200 $2,000 $7,200
96,400
kWh
-
04 2.2514: Cover open tanks $2,500 - $2,500
33,800
kWh
-
05 2.7311: Ventilation system to shut off when room is not in use $1,560 - $1,560
20,800
kWh
-
06 2.7121: Utilize daylight whenever possible in lieu of artificial light $1,370 - $1,000
13,400
kWh
$370
-
kW-mo/yr
07 2.7121: Utilize daylight whenever possible in lieu of artificial light $1,150 - $1,150
15,370
kWh
-
08 2.4314: Use synthetic lubricant $320 - $260
3,500
kWh
$60
-
kW-mo/yr
TOTAL RECOMMENDED $36,100 $3,520 $31,570
421,970
kWh
$4,530
-
kW-mo/yr
TOTAL IMPLEMENTED $34,950 $3,520 $30,420
406,600
kWh
$4,530
-
kW-mo/yr
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs