ITAC Assessment: AM0486
ITAC logo
ITAC Assessment: AM0486
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Refrigeration and food processing pressure vessels
NAICS 332410: Power Boiler and Heat Exchanger Manufacturing
SIC 3585: Air-Conditioning and Warm Air Heating Equipment and Commercial and Industrial Refrigeration Equipment
Sales Range $10
M
to 50
M
# of Employees 80
Plant Area 48,000
ft2
Annual Production 1,230
pieces
Production Hrs. Annual 4,000
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $68,666 1,110,676
kWh
Electricity Demand $22,133 2,937
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $4,951 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,951

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Ancillary Material Cost Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $1,394 $50 $1,033
16,666
kWh
$361
-
kW-mo/yr
-
02 2.7145: Install skylights $1,020 - $450
7,236
kWh
$570
-
kW-mo/yr
-
03 2.7124: Make a practice of turning off lights when not needed $710 $290 $480
7,680
kWh
$230
-
kW-mo/yr
-
04 2.7261: Install timers and/or thermostats $702 - $414
6,671
kWh
$288
-
kW-mo/yr
-
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $502 $400 $372
5,994
kWh
$130
-
kW-mo/yr
-
06 2.7142: Utilize higher efficiency lamps and/or ballasts $448 $307 $122
1,960
kWh
$19
-
kW-mo/yr
$307
07 3.6192: Use a less expensive method of waste removal $175 $700 - - $175
TOTAL RECOMMENDED $4,951 $1,747 $2,871
46,207
kWh
$1,598
-
kW-mo/yr
$482
TOTAL IMPLEMENTED $4,951 $1,747 $2,871
46,207
kWh
$1,598
-
kW-mo/yr
$482
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs