Assessment Year | 2004 |
---|---|
Principal Product | Pipe threading |
NAICS | 332996: Fabricated Pipe and Pipe Fitting Manufacturing |
SIC | 3498: Fabricated Pipe and Pipe Fittings |
Sales Range | $10 M to 50M |
# of Employees | 185 |
Plant Area |
174,000
ft2
|
Annual Production | 105,000
pieces
|
Production Hrs. Annual | 6,040
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $227,158 | 5,404,389 |
kWh
|
$0.042 |
Electricity Fees | $84,265 | - |
|
- |
Natural Gas | $69,203 | 7,888 |
MMBtu
|
$8.77 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $132,795 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $118,005 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.8121: Apply for tax-free status for energy purchases | $71,800 | $17,950 | - | - | - | $35,900 | - | $35,900 | |
02 | 2.4239: Eliminate or reduce compressed air usage | $24,000 | $1,920 |
$24,000
417,700
kWh
|
- | - | - | - | - | |
03 | 2.8113: Purchase gas directly from a contract gas supplier | $12,560 | $5,000 | - | - | - | - | $12,560 | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $5,630 | $20 |
$5,630
97,700
kWh
|
- | - | - | - | - | |
05 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $3,730 | - |
$3,730
64,800
kWh
|
- | - | - | - | - | |
06 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $3,480 | - |
$3,480
60,400
kWh
|
- | - | - | - | - | |
07 | 2.2511: Insulate bare equipment | $3,430 | $900 | - |
$3,430
-
MMBtu
|
- | - | - | - | |
08 | 2.7145: Install skylights | $2,600 | $6,200 |
$2,600
45,500
kWh
|
- | - | - | - | - | |
09 | 2.7145: Install skylights | $2,230 | $5,400 |
$2,230
38,600
kWh
|
- | - | - | - | - | |
10 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,350 | $200 |
$1,350
23,500
kWh
|
- | - | - | - | - | |
11 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,255 | $360 |
$400
7,000
kWh
|
- | $855 | - | - | - | |
12 | 2.8123: Pay utility bills on time | $370 | - | - | - | - | $370 | - | - | |
13 | 2.7124: Make a practice of turning off lights when not needed | $360 | $27 |
$360
6,245
kWh
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $132,795 | $37,977 |
$43,780
761,445
kWh
|
$3,430
-
MMBtu
|
$855 | $36,270 | $12,560 | $35,900 | ||
TOTAL IMPLEMENTED | $118,005 | $27,577 |
$41,550
722,845
kWh
|
$3,430
-
MMBtu
|
$855 | $36,270 | - | $35,900 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs