ITAC Assessment: AM0448
ITAC logo
ITAC Assessment: AM0448
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Steel forgings
NAICS 332111: Iron and Steel Forging
SIC 3325: Steel Foundries, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 153
Plant Area 280,000
ft2
Annual Production 24,000,000
lb
Production Hrs. Annual 6,576
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $313,689 8,139,600
kWh
Electricity Demand $144,260 19,654
kW-mo/yr
Electricity Fees $4,783 -
Natural Gas $1,112,442 250,102
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $1,335,832 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,330,632

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
01 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat $1,266,100 $805,000 $144,700
3,288,000
kWh
$41,200
-
kW-mo/yr
$(-119,800.0)
-
MMBtu
- $1,200,000
02 2.1135: Repair furnaces and oven doors so that they seal efficiently $24,300 $5,730 - - $24,300
-
MMBtu
- -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $16,000 $2,000 $16,000
363,900
kWh
- - - -
04 2.4239: Eliminate or reduce compressed air usage $5,200 $1,550 $5,200
117,500
kWh
- - - -
05 2.4314: Use synthetic lubricant $4,032 - $4,032
68,397
kWh
- - - -
06 2.2511: Insulate bare equipment $2,200 $2,000 $2,200
49,900
kWh
- - - -
07 2.4231: Reduce the pressure of compressed air to the minimum required $2,120 $25 $1,650
37,400
kWh
$470
-
kW-mo/yr
- - -
08 2.7124: Make a practice of turning off lights when not needed $500 $70 $340
7,640
kWh
$160
-
kW-mo/yr
- - -
09 2.7121: Utilize daylight whenever possible in lieu of artificial light $1,600 - $1,600
36,400
kWh
- - - -
10 3.6192: Use a less expensive method of waste removal $13,780 - - - - $13,780 -
TOTAL RECOMMENDED $1,335,832 $816,375 $175,722
3,969,137
kWh
$41,830
-
kW-mo/yr
$(-95,500.0)
-
MMBtu
$13,780 $1,200,000
TOTAL IMPLEMENTED $1,330,632 $814,825 $170,522
3,851,637
kWh
$41,830
-
kW-mo/yr
$(-95,500.0)
-
MMBtu
$13,780 $1,200,000
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs