ITAC Assessment: AM0422
ITAC logo
ITAC Assessment: AM0422
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Machinery noise control equipment
NAICS
n/a
SIC 3569: General Industrial Machinery and Equipment, Not Elsewhere
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 23,000
ft2
Annual Production 12,000
ton
Production Hrs. Annual 1,990
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $46,548 560,256
kWh
Electricity Demand $6,975 2,370
kW-mo/yr
Electricity Fees $592 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $64,760 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $17,035

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 4.446: Automate finishing process $47,350 $110,240 - $1,250
-
kW-mo/yr
$46,100 - -
02 4.211: Consider use / purchase of bulk materials where possible $13,580 $5,270 - - $1,520 - $12,060
03 2.4231: Reduce the pressure of compressed air to the minimum required $1,545 $30 $970
14,200
kWh
$575
-
kW-mo/yr
- - -
04 2.7124: Make a practice of turning off lights when not needed $780 $50 $590
8,600
kWh
$190
-
kW-mo/yr
- - -
05 2.8123: Pay utility bills on time $645 - - - - $645 -
06 2.3212: Optimize plant power factor $375 $840 - $375
-
kW-mo/yr
- - -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $345 $310 $160
2,330
kWh
$20
-
kW-mo/yr
$165 - -
08 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $140 $50 $140
2,080
kWh
- - - -
TOTAL RECOMMENDED $64,760 $116,790 $1,860
27,210
kWh
$2,410
-
kW-mo/yr
$47,785 $645 $12,060
TOTAL IMPLEMENTED $17,035 $5,710 $1,860
27,210
kWh
$785
-
kW-mo/yr
$1,685 $645 $12,060
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs