ITAC Assessment: AM0390
ITAC logo
ITAC Assessment: AM0390
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Solid and finger joint moldings/frames, closet rounds, wood
NAICS
n/a
SIC 2431: Millwork
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area 88,300
ft2
Annual Production 1,676,000
pieces
Production Hrs. Annual 4,080
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $119,174 2,847,146
kWh
Electricity Demand $76,346 9,576
kW-mo/yr
Natural Gas $20,553 3,807
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $148,915 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $57,055

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings LPG Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings
01 4.445: Install equipment to move product $51,050 $162,000 n/a $(-850.0)
(-30,400)
kWh
$(-1,100.0)
-
kW-mo/yr
- - - $53,000 -
02 4.445: Install equipment to move product $51,050 $150,000 $(-850.0)
(-30,400)
kWh
$(-1,100.0)
-
kW-mo/yr
- - - $53,000 -
03 3.5311: Recover and reuse waste material $16,100 - - - - - $16,100
-
lb
- -
04 2.7231: Use radiant heater for spot heating $19,350 $4,700 - - $2,260
-
MMBtu
$17,090
-
MMBtu
- - -
05 2.2437: Recover waste heat from equipment $3,300 $530 - - - $3,300
-
MMBtu
- - -
06 3.5311: Recover and reuse waste material $1,600 - - - - - $1,600
-
lb
- -
07 2.8121: Apply for tax-free status for energy purchases $1,545 $3,090 - - - - - - $1,545
08 2.4222: Install adequate dryers on air lines to eliminate blowdown $1,100 $780 $1,100
39,300
kWh
- - - - - -
09 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,100 $200 $1,100
39,000
kWh
- - - - - -
10 2.7124: Make a practice of turning off lights when not needed $1,080 $50 $610
11,500
kWh
$470
-
kW-mo/yr
- - - - -
11 2.4231: Reduce the pressure of compressed air to the minimum required $960 $20 $410
14,800
kWh
$550
-
kW-mo/yr
- - - - -
12 2.7121: Utilize daylight whenever possible in lieu of artificial light $680 - $680
24,300
kWh
- - - - - -
TOTAL RECOMMENDED $148,915 $321,370 $2,200
68,100
kWh
$(-1,180.0)
-
kW-mo/yr
$2,260
-
MMBtu
$20,390
-
MMBtu
$17,700
-
lb
$106,000 $1,545
TOTAL IMPLEMENTED $57,055 $153,340 $1,540
44,400
kWh
$(-630.0)
-
kW-mo/yr
- - $1,600
-
lb
$53,000 $1,545
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings LPG Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs