ITAC Assessment: OK0404
ITAC logo
ITAC Assessment: OK0404
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product Portland Cement, Low Alkali, and Mas
NAICS
n/a
SIC 3241: Cement, Hydraulic
Sales Range $10
M
to 50
M
# of Employees 160
Plant Area 15,000
ft2
Annual Production 600,000
ton
Production Hrs. Annual 8,736
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $2,728,226 78,798,360
kWh
Natural Gas $339,593 158,522
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $171,268 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $156,285

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.4133: Use most efficient type of electric motors $53,433 $110,746 $53,433
1,526,671
kWh
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $102,852 $309,735 $102,852
2,938,746
kWh
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $14,983 $30,075 $14,983
428,195
kWh
TOTAL RECOMMENDED $171,268 $450,556 $171,268
4,893,612
kWh
TOTAL IMPLEMENTED $156,285 $420,481 $156,285
4,465,417
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs