ITAC Assessment: AM0368
ITAC logo
ITAC Assessment: AM0368
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Fiberglass Strands for reinforcement
NAICS
n/a
SIC 3229: Pressed and Blown Glass and Glassware, Not Elsewhere Classified
Sales Range $100
M
to 500
M
# of Employees 765
Plant Area 500,000
ft2
Annual Production 275,000,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $3,858,395 188,208,092
kWh
Electricity Demand $1,626,729 271,300
kW-mo/yr
Natural Gas $2,752,413 1,308,600
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $2,713,841 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $167,001

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Fuel Oil #2 Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings Water Consumption Savings Primary Product Savings By-product Production Savings
01 3.5313: Increase amount of waste recovered for resale $1,224,000 $234,000 - - - $(-32,000.0)
-
MMBtu
- $116,000
-
lb
$(-77,000.0) - - - - $1,217,000 -
02 3.5313: Increase amount of waste recovered for resale $339,020 $481,000 - - - - - $180,020
-
lb
- - - - - - $159,000
03 3.1192: Reduce scrap production $327,000 $45,000 $25,000
1,219,226
kWh
- - - - - $73,000 - $126,000 - - $103,000 -
04 3.7211: Modify material application methods $207,000 - - - - - - - - - - $207,000 - - -
05 4.231: Purchase equipment instead of leasing $131,000 $317,000 - - - - - - - $131,000 - - - - -
06 3.1192: Reduce scrap production $54,000 $120,000 - - - - - - $(-182,000.0) - $98,000 - - $138,000 -
07 3.1191: Change procedures / equipment / operating conditions $85,560 $3,500 - - - - $3,120
-
Tgal
- $(-940.0) $80,000 - - $3,380
-
Tgal
- -
08 2.2414: Use waste heat from hot flue gases to preheat $85,000 $100,000 - - $85,000
-
MMBtu
- - - - - - - - - -
09 3.4113: Treat and reuse rinse waters $80,300 $242,500 - - - - $38,500
-
Tgal
- - - - - $41,800
-
Tgal
- -
10 3.6192: Use a less expensive method of waste removal $72,000 $68,000 - - - - - - $72,000 - - - - - -
11 2.7231: Use radiant heater for spot heating $72,000 $26,400 - - $72,000
-
MMBtu
- - - - - - - - - -
12 2.7124: Make a practice of turning off lights when not needed $10,591 - $6,048
302,462
kWh
$4,543
-
kW-mo/yr
- - - - - - - - - - -
13 2.4314: Use synthetic lubricant $10,060 - $7,140
356,975
kWh
$2,920
-
kW-mo/yr
- - - - - - - - - - -
14 4.652: Replace existing equipment with more suitable substitutes $8,800 - - - - - - - - $8,800 - - - - -
15 2.2126: Lower operating pressure of condenser (steam) $3,400 - - - $3,400
-
MMBtu
- - - - - - - - - -
16 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,040 $1,500 $3,040
152,110
kWh
- - - - - - - - - - - -
17 2.7142: Utilize higher efficiency lamps and/or ballasts $1,070 $3,400 $340
16,999
kWh
$140
-
kW-mo/yr
- - - - $590 - - - - - -
TOTAL RECOMMENDED $2,713,841 $1,642,300 $41,568
2,047,772
kWh
$7,603
-
kW-mo/yr
$160,400
-
MMBtu
$(-32,000.0)
-
MMBtu
$41,620
-
Tgal
$296,020
-
lb
$(-114,350.0) $219,800 $224,000 $207,000 $45,180
-
Tgal
$1,458,000 $159,000
TOTAL IMPLEMENTED $167,001 $315,400 $9,428
471,571
kWh
$4,683
-
kW-mo/yr
- - $38,500
-
Tgal
- $72,590 - - - $41,800
-
Tgal
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Fuel Oil #2 Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings Water Consumption Savings Primary Product Savings By-product Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs