ITAC Assessment: AM0349
ITAC logo
ITAC Assessment: AM0349
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product spiral wound and heat exchanger gaskets
NAICS
n/a
SIC 3053: Gaskets, Packing, and Sealing Devices
Sales Range $10
M
to 50
M
# of Employees 180
Plant Area 52,000
ft2
Annual Production 2,000,000
pieces
Production Hrs. Annual 4,857
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $122,861 1,976,260
kWh
Electricity Demand $24,573 8,287
kW-mo/yr
Electricity Fees $522 -
Natural Gas $13,266 2,506
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $238,892 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $153,997

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Liquid (non-haz) Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings
01 4.446: Automate finishing process $108,500 $30,000 - - - - - $108,500
02 4.422: Utilize outside contracting $80,000 $160,000 - - - - - $80,000
03 2.3212: Optimize plant power factor $13,380 $15,600 - $13,380
-
kW-mo/yr
- - - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $10,540 $1,000 $10,540
202,814
kWh
- - - - -
05 3.5315: Lease / purchase baler; sell cardboard to recycler $12,495 $5,500 - - - - $12,495
-
lb
-
06 3.5316: Contract a wood pallet recycling company $7,630 - - - - - $7,630
-
lb
-
07 3.2123: Convert to high volume low pressure (hvlp) paint guns $3,645 $590 - - $3,645
-
gal
- - -
08 3.8131: Use water-based adhesives $1,275 $1,030 - - - $1,275
-
gal
- -
09 2.7111: Reduce illumination to minimum necessary levels $880 $425 $600
11,430
kWh
$280
-
kW-mo/yr
- - - -
10 2.7121: Utilize daylight whenever possible in lieu of artificial light $370 - $370
9,965
kWh
- - - - -
11 4.821: Pay bills on time to avoid late fees $177 - - - - - - $177
TOTAL RECOMMENDED $238,892 $214,145 $11,510
224,209
kWh
$13,660
-
kW-mo/yr
$3,645
-
gal
$1,275
-
gal
$20,125
-
lb
$188,677
TOTAL IMPLEMENTED $153,997 $53,130 $10,540
202,814
kWh
$13,380
-
kW-mo/yr
- $1,275
-
gal
$20,125
-
lb
$108,677
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Other Liquid (non-haz) Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs