ITAC Assessment: AM0338
ITAC logo
ITAC Assessment: AM0338
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Cut and polished granite blocks and slabs
NAICS
n/a
SIC 3281: Cut Stone and Stone Products
Sales Range $10
M
to 50
M
# of Employees 235
Plant Area 184,420
ft2
Annual Production 29,000
ton
Production Hrs. Annual 8,568
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $347,764 7,788,980
kWh
Electricity Demand $70,563 23,204
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $68,340 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $60,280

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Liquid (haz) Savings Personnel Changes Savings Administrative Changes Savings
01 2.8123: Pay utility bills on time $20,800 - - - - - $20,800
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $16,000 $500 $16,000
380,129
kWh
- - - -
03 3.8211: Convert to aqueous cleaning system $10,320 $10,300 - - $10,320
-
gal
- -
04 4.611: Begin a practice of predictive / preventative maintenance $8,800 $900 $750
17,292
kWh
- - $8,050 -
05 2.4226: Use / purchase optimum sized compressor $4,985 $2,435 $4,080
97,304
kWh
$905
-
kW-mo/yr
- - -
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,000 $350 $4,000
94,959
kWh
- - - -
07 2.7145: Install skylights $1,525 $410 $1,150
27,550
kWh
$375
-
kW-mo/yr
- - -
08 2.7121: Utilize daylight whenever possible in lieu of artificial light $2,650 - $2,650
63,013
kWh
- - - -
09 2.7145: Install skylights $(-1,410.0) $2,230 $520
12,309
kWh
- - $(-1,930.0) -
10 2.7145: Install skylights $370 $470 $370
8,792
kWh
- - - -
11 2.7142: Utilize higher efficiency lamps and/or ballasts $300 - $300
7,034
kWh
- - - -
TOTAL RECOMMENDED $68,340 $17,595 $29,820
708,382
kWh
$1,280
-
kW-mo/yr
$10,320
-
gal
$6,120 $20,800
TOTAL IMPLEMENTED $60,280 $13,995 $27,880
662,955
kWh
$1,280
-
kW-mo/yr
$10,320
-
gal
- $20,800
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Other Liquid (haz) Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs