ITAC Assessment: AM0323
ITAC logo
ITAC Assessment: AM0323
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Steel wire drawing, straight cut steel wire, welded wire mes
NAICS
n/a
SIC 3315: Steel Wiredrawing and Steel Nails and Spikes
Sales Range $10
M
to 50
M
# of Employees 122
Plant Area 103,700
ft2
Annual Production 60,000
ton
Production Hrs. Annual 8,544
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $160,353 5,783,705
kWh
Electricity Demand $87,951 13,106
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $47,365 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings Administrative Changes Savings
01 3.1192: Reduce scrap production $22,500 - - - - $22,500
-
lb
-
02 3.7198: Reduce / eliminate use of disposable product $10,600 $150 - - - $10,600
-
lb
-
03 3.5311: Recover and reuse waste material $4,590 - - - - $4,590
-
lb
-
04 2.4314: Use synthetic lubricant $2,320 - $1,730
61,841
kWh
$590
-
kW-mo/yr
- - -
05 2.8112: Combine utility meters $2,310 $2,700 - - - - $2,310
06 2.4133: Use most efficient type of electric motors $1,595 $4,300 $1,200
42,790
kWh
$395
-
kW-mo/yr
- - -
07 4.231: Purchase equipment instead of leasing $1,420 $1,870 - - - - $1,420
08 2.7123: Keep lamps and reflectors clean $1,260 - $1,260
45,135
kWh
- - - -
09 2.7124: Make a practice of turning off lights when not needed $520 $63 $460
7,034
kWh
$60
-
kW-mo/yr
- - -
10 3.6194: Ship hydraulic oil to secondary fuel program $250 - - - $250
-
gal
- -
TOTAL RECOMMENDED $47,365 $9,083 $4,650
156,800
kWh
$1,045
-
kW-mo/yr
$250
-
gal
$37,690
-
lb
$3,730
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs