| Assessment Year | 1998 |
|---|---|
| Principal Product | Steel wire drawing, straight cut steel wire, welded wire mes |
| NAICS |
n/a
|
| SIC | 3315: Steel Wiredrawing and Steel Nails and Spikes |
| Sales Range | $10 M to 50M |
| # of Employees | 122 |
| Plant Area |
103,700
ft2
|
| Annual Production | 60,000
ton
|
| Production Hrs. Annual | 8,544
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $160,353 | 5,783,705 |
kWh
|
$0.028 |
| Electricity Demand | $87,951 | 13,106 |
kW-mo/yr
|
$6.71 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $47,365 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 3.1192: Reduce scrap production | $22,500 | - | - | - | - |
$22,500
-
lb
|
- | |
| 02 | 3.7198: Reduce / eliminate use of disposable product | $10,600 | $150 | - | - | - |
$10,600
-
lb
|
- | |
| 03 | 3.5311: Recover and reuse waste material | $4,590 | - | - | - | - |
$4,590
-
lb
|
- | |
| 04 | 2.4314: Use synthetic lubricant | $2,320 | - |
$1,730
61,841
kWh
|
$590
-
kW-mo/yr
|
- | - | - | |
| 05 | 2.8112: Combine utility meters | $2,310 | $2,700 | - | - | - | - | $2,310 | |
| 06 | 2.4133: Use most efficient type of electric motors | $1,595 | $4,300 |
$1,200
42,790
kWh
|
$395
-
kW-mo/yr
|
- | - | - | |
| 07 | 4.231: Purchase equipment instead of leasing | $1,420 | $1,870 | - | - | - | - | $1,420 | |
| 08 | 2.7123: Keep lamps and reflectors clean | $1,260 | - |
$1,260
45,135
kWh
|
- | - | - | - | |
| 09 | 2.7124: Make a practice of turning off lights when not needed | $520 | $63 |
$460
7,034
kWh
|
$60
-
kW-mo/yr
|
- | - | - | |
| 10 | 3.6194: Ship hydraulic oil to secondary fuel program | $250 | - | - | - |
$250
-
gal
|
- | - | |
| TOTAL RECOMMENDED | $47,365 | $9,083 |
$4,650
156,800
kWh
|
$1,045
-
kW-mo/yr
|
$250
-
gal
|
$37,690
-
lb
|
$3,730 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs