Assessment Year | 1998 |
---|---|
Principal Product | Underground fiberglass fuel storage tanks, fiberglass manhol |
NAICS |
n/a
|
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 50 |
Plant Area |
128,500
ft2
|
Annual Production | 3,500
pieces
|
Production Hrs. Annual | 4,867
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $106,700 | 3,542,790 |
kWh
|
$0.030 |
Electricity Demand | $80,665 | 9,691 |
kW-mo/yr
|
$8.32 |
Natural Gas | $36,775 | 9,060 |
MMBtu
|
$4.06 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $19,975 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $15,480 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2211: Use optimum temperature | $11,790 | - | - | - |
$11,790
-
MMBtu
|
- | - | |
02 | 4.231: Purchase equipment instead of leasing | $3,110 | $5,400 | - | - | - | - | $3,110 | |
03 | 2.7124: Make a practice of turning off lights when not needed | $2,430 | $160 |
$2,430
83,822
kWh
|
- | - | - | - | |
04 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $875 | - | - |
$875
-
kW-mo/yr
|
- | - | - | |
05 | 3.1191: Change procedures / equipment / operating conditions | $840 | $1,500 | - | - | - |
$840
-
gal
|
- | |
06 | 2.7145: Install skylights | $510 | $1,860 |
$510
17,585
kWh
|
- | - | - | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $420 | $100 |
$420
14,654
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $19,975 | $9,020 |
$3,360
116,061
kWh
|
$875
-
kW-mo/yr
|
$11,790
-
MMBtu
|
$840
-
gal
|
$3,110 | ||
TOTAL IMPLEMENTED | $15,480 | $1,760 |
$2,850
98,476
kWh
|
- |
$11,790
-
MMBtu
|
$840
-
gal
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs