ITAC Assessment: AM0183
ITAC logo
ITAC Assessment: AM0183
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product gaskets
NAICS
n/a
SIC 3053: Gaskets, Packing, and Sealing Devices
Sales Range $10
M
to 50
M
# of Employees 300
Plant Area
n/a
Annual Production 3,360,000
lb
Production Hrs. Annual 4,000
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $232,727 3,861,665
kWh
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $13,645 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $9,005

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $7,600 $900 $7,600
185,522
kWh
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,260 $1,570 $1,260
25,498
kWh
03 2.6231: Utilize controls to operate equipment only when needed $1,640 $6,410 $1,640
40,152
kWh
04 2.3212: Optimize plant power factor $3,000 $9,000 $3,000
-
kWh
05 2.4133: Use most efficient type of electric motors $145 $820 $145
1,465
kWh
TOTAL RECOMMENDED $13,645 $18,700 $13,645
252,637
kWh
TOTAL IMPLEMENTED $9,005 $3,290 $9,005
212,485
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs