ITAC Assessment: AM0172
ITAC logo
ITAC Assessment: AM0172
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product petroleum pipe insulation
NAICS
n/a
SIC 3292: Asbestos Products
Sales Range $5
M
to 10
M
# of Employees 0
Plant Area 64,000
ft2
Annual Production 300,000
thousand feet
Production Hrs. Annual 2,900
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $53,858 976,260
kWh
LPG $9,205 946
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $17,240 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $13,410

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $5,300 $112 $5,300
50,410
kWh
02 2.3212: Optimize plant power factor $4,110 $8,000 $4,110
-
kWh
03 2.4226: Use / purchase optimum sized compressor $3,600 - $3,600
37,222
kWh
04 2.7142: Utilize higher efficiency lamps and/or ballasts $3,280 $7,390 $3,280
37,808
kWh
05 2.7142: Utilize higher efficiency lamps and/or ballasts $550 $22 $550
5,275
kWh
06 2.4231: Reduce the pressure of compressed air to the minimum required $280 - $280
11,137
kWh
07 2.6212: Turn off equipment during breaks, reduce operating time $120 - $120
4,689
kWh
TOTAL RECOMMENDED $17,240 $15,524 $17,240
146,541
kWh
TOTAL IMPLEMENTED $13,410 $8,112 $13,410
103,458
kWh
Yearly Savings* Imp'd Cost* Electricity Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs