| Assessment Year | 1992 |
|---|---|
| Principal Product | envelopes |
| NAICS |
n/a
|
| SIC | 2677: Envelopes |
| Sales Range | $10 M to 50M |
| # of Employees | 170 |
| Plant Area |
125,000
ft2
|
| Annual Production | 23,000,000,000
pieces
|
| Production Hrs. Annual | 6,312
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $286,959 | 5,907,093 |
kWh
|
$0.049 |
| Natural Gas | $26,163 | 5,037 |
MMBtu
|
$5.19 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $40,645 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $31,350 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.6222: Use drying oven (batch type) on alternate days or other optimum schedule to run equipment with full loads | $23,570 | $1,350 |
$23,570
511,430
kWh
|
- | |
| 02 | 2.7292: Lower ceiling to reduce conditioned space | $6,300 | $3,630 | - |
$6,300
-
MMBtu
|
|
| 03 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $3,915 | $3,450 |
$8,730
189,332
kWh
|
$(-4,815.0)
-
MMBtu
|
|
| 04 | 2.5123: Reduce fluid flow rates | $2,710 | - |
$2,710
105,803
kWh
|
- | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,750 | - |
$1,750
68,581
kWh
|
- | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,330 | $2,520 |
$1,330
29,015
kWh
|
- | |
| 07 | 2.7111: Reduce illumination to minimum necessary levels | $920 | $920 |
$920
19,930
kWh
|
- | |
| 08 | 2.6232: Install set-back timers | $150 | $190 |
$150
5,862
kWh
|
- | |
| TOTAL RECOMMENDED | $40,645 | $12,060 |
$39,160
929,953
kWh
|
$1,485
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $31,350 | $7,690 |
$25,050
546,307
kWh
|
$6,300
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs