ITAC Assessment: AM0162
ITAC logo
ITAC Assessment: AM0162
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1992
Principal Product ship repair
NAICS
n/a
SIC 3731: Ship Building and Repairing
Sales Range $5
M
to 10
M
# of Employees 70
Plant Area 5,900
ft2
Annual Production 400
pieces
Production Hrs. Annual 6,060
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $90,034 1,145,369
kWh
Other Energy $9,118 149
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $5,580 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,580

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.6212: Turn off equipment during breaks, reduce operating time $2,720 $782 $2,720
67,995
kWh
02 2.4222: Install adequate dryers on air lines to eliminate blowdown $1,150 $5,746 $1,150
36,635
kWh
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,010 $300 $1,010
25,205
kWh
04 2.7111: Reduce illumination to minimum necessary levels $700 $215 $700
9,672
kWh
TOTAL RECOMMENDED $5,580 $7,043 $5,580
139,507
kWh
TOTAL IMPLEMENTED $5,580 $7,043 $5,580
139,507
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs