ITAC Assessment: AM0161
ITAC logo
ITAC Assessment: AM0161
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1992
Principal Product SHIP BUILDING & REPAIRS
NAICS
n/a
SIC 3731: Ship Building and Repairing
Sales Range $5
M
to 10
M
# of Employees 75
Plant Area
n/a
Annual Production 300
pieces
Production Hrs. Annual 4,301
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $103,940 1,453,986
kWh
Other Energy $11,176 203
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $23,040 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $16,135

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,600 $630 $5,600
114,302
kWh
- -
02 2.3521: Reduce load on electrical conductor to reduce heating losses $4,700 $2,255 $4,700
96,131
kWh
- -
03 2.3131: Reschedule plant operations or reduce load to avoid peaks $3,855 - $3,855
-
kWh
- -
04 2.7111: Reduce illumination to minimum necessary levels $3,290 $985 $3,290
43,083
kWh
- -
05 2.7111: Reduce illumination to minimum necessary levels $2,420 - $2,420
49,238
kWh
- -
06 2.8114: Change rate schedules or other changes in utility service $2,205 $5,050 $1,250
-
kWh
- $955
07 2.6218: Turn off equipment when not in use $690 - $690
14,068
kWh
- -
08 2.7261: Install timers and/or thermostats $280 $450 $150
4,689
kWh
$130
-
MMBtu
-
TOTAL RECOMMENDED $23,040 $9,370 $21,955
321,511
kWh
$130
-
MMBtu
$955
TOTAL IMPLEMENTED $16,135 $2,065 $16,005
225,380
kWh
$130
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs