Assessment Year | 1992 |
---|---|
Principal Product | SHIP BUILDING & REPAIRS |
NAICS |
n/a
|
SIC | 3731: Ship Building and Repairing |
Sales Range | $5 M to 10M |
# of Employees | 75 |
Plant Area |
n/a
|
Annual Production | 300
pieces
|
Production Hrs. Annual | 4,301
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $103,940 | 1,453,986 |
kWh
|
$0.071 |
Other Energy | $11,176 | 203 |
MMBtu
|
$55.05 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $23,040 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $16,135 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,600 | $630 |
$5,600
114,302
kWh
|
- | - | |
02 | 2.3521: Reduce load on electrical conductor to reduce heating losses | $4,700 | $2,255 |
$4,700
96,131
kWh
|
- | - | |
03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $3,855 | - |
$3,855
-
kWh
|
- | - | |
04 | 2.7111: Reduce illumination to minimum necessary levels | $3,290 | $985 |
$3,290
43,083
kWh
|
- | - | |
05 | 2.7111: Reduce illumination to minimum necessary levels | $2,420 | - |
$2,420
49,238
kWh
|
- | - | |
06 | 2.8114: Change rate schedules or other changes in utility service | $2,205 | $5,050 |
$1,250
-
kWh
|
- | $955 | |
07 | 2.6218: Turn off equipment when not in use | $690 | - |
$690
14,068
kWh
|
- | - | |
08 | 2.7261: Install timers and/or thermostats | $280 | $450 |
$150
4,689
kWh
|
$130
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $23,040 | $9,370 |
$21,955
321,511
kWh
|
$130
-
MMBtu
|
$955 | ||
TOTAL IMPLEMENTED | $16,135 | $2,065 |
$16,005
225,380
kWh
|
$130
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs