| Assessment Year | 1992 |
|---|---|
| Principal Product | SHIP BUILDING & REPAIRS |
| NAICS |
n/a
|
| SIC | 3731: Ship Building and Repairing |
| Sales Range | $5 M to 10M |
| # of Employees | 75 |
| Plant Area |
n/a
|
| Annual Production | 300
pieces
|
| Production Hrs. Annual | 4,301
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $103,940 | 1,453,986 |
kWh
|
$0.071 |
| Other Energy | $11,176 | 203 |
MMBtu
|
$55.05 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $23,040 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $16,135 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,600 | $630 |
$5,600
114,302
kWh
|
- | - | |
| 02 | 2.3521: Reduce load on electrical conductor to reduce heating losses | $4,700 | $2,255 |
$4,700
96,131
kWh
|
- | - | |
| 03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $3,855 | - |
$3,855
-
kWh
|
- | - | |
| 04 | 2.7111: Reduce illumination to minimum necessary levels | $3,290 | $985 |
$3,290
43,083
kWh
|
- | - | |
| 05 | 2.7111: Reduce illumination to minimum necessary levels | $2,420 | - |
$2,420
49,238
kWh
|
- | - | |
| 06 | 2.8114: Change rate schedules or other changes in utility service | $2,205 | $5,050 |
$1,250
-
kWh
|
- | $955 | |
| 07 | 2.6218: Turn off equipment when not in use | $690 | - |
$690
14,068
kWh
|
- | - | |
| 08 | 2.7261: Install timers and/or thermostats | $280 | $450 |
$150
4,689
kWh
|
$130
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $23,040 | $9,370 |
$21,955
321,511
kWh
|
$130
-
MMBtu
|
$955 | ||
| TOTAL IMPLEMENTED | $16,135 | $2,065 |
$16,005
225,380
kWh
|
$130
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs