ITAC Assessment: AM0149
ITAC logo
ITAC Assessment: AM0149
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1992
Principal Product MASTICS,METAL SHEETS,ADHESIVE
NAICS
n/a
SIC 2851: Paints, Varnishes, Lacquers, Enamels, and Allied Products
Sales Range $10
M
to 50
M
# of Employees 30
Plant Area
n/a
Annual Production 5,000,000
lb
Production Hrs. Annual 2,305
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $46,519 466,589
kWh
Natural Gas $5,257 1,179
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $3,977 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,107

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.3131: Reschedule plant operations or reduce load to avoid peaks $2,390 - $2,390
(-4,689)
kWh
02 2.3131: Reschedule plant operations or reduce load to avoid peaks $870 - $870
-
kWh
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $170 $160 $170
2,345
kWh
04 2.6232: Install set-back timers $150 $120 $150
2,052
kWh
05 2.4133: Use most efficient type of electric motors $397 $373 $397
4,103
kWh
TOTAL RECOMMENDED $3,977 $653 $3,977
3,811
kWh
TOTAL IMPLEMENTED $3,107 $653 $3,107
3,811
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs