Assessment Year | 1992 |
---|---|
Principal Product | BREAD,BROWNIES,COOKIES |
NAICS |
n/a
|
SIC | 2051: Bread and Other Bakery Products, Except Cookies and Crackers |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
n/a
|
Annual Production | 100,000,000
pieces
|
Production Hrs. Annual | 2,150
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $123,678 | 2,524,326 |
kWh
|
$0.049 |
Natural Gas | $100,345 | 33,467 |
MMBtu
|
$3.00 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $7,030 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,910 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.2136: Install / repair insulation on steam lines | $2,620 | $7,934 | - |
$2,620
-
MMBtu
|
- | |
02 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,400 | $540 | - |
$1,400
-
MMBtu
|
- | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,120 | $2,400 |
$1,120
16,120
kWh
|
- | - | |
04 | 2.6232: Install set-back timers | $930 | - |
$930
20,809
kWh
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $275 | - |
$290
4,103
kWh
|
- | $(-15.0) | |
06 | 2.4312: Improve lubrication practices | $385 | - |
$385
4,396
kWh
|
- | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $230 | $220 |
$230
7,620
kWh
|
- | - | |
08 | 2.4133: Use most efficient type of electric motors | $70 | $100 |
$70
879
kWh
|
- | - | |
TOTAL RECOMMENDED | $7,030 | $11,194 |
$3,025
53,927
kWh
|
$4,020
-
MMBtu
|
$(-15.0) | ||
TOTAL IMPLEMENTED | $5,910 | $8,794 |
$1,905
37,807
kWh
|
$4,020
-
MMBtu
|
$(-15.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs