ITAC Assessment: AM0146
ITAC logo
ITAC Assessment: AM0146
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1992
Principal Product BREAD,BROWNIES,COOKIES
NAICS
n/a
SIC 2051: Bread and Other Bakery Products, Except Cookies and Crackers
Sales Range $10
M
to 50
M
# of Employees 200
Plant Area
n/a
Annual Production 100,000,000
pieces
Production Hrs. Annual 2,150
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $123,678 2,524,326
kWh
Natural Gas $100,345 33,467
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $7,030 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,910

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.2136: Install / repair insulation on steam lines $2,620 $7,934 - $2,620
-
MMBtu
-
02 2.1233: Analyze flue gas for proper air/fuel ratio $1,400 $540 - $1,400
-
MMBtu
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,120 $2,400 $1,120
16,120
kWh
- -
04 2.6232: Install set-back timers $930 - $930
20,809
kWh
- -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $275 - $290
4,103
kWh
- $(-15.0)
06 2.4312: Improve lubrication practices $385 - $385
4,396
kWh
- -
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $230 $220 $230
7,620
kWh
- -
08 2.4133: Use most efficient type of electric motors $70 $100 $70
879
kWh
- -
TOTAL RECOMMENDED $7,030 $11,194 $3,025
53,927
kWh
$4,020
-
MMBtu
$(-15.0)
TOTAL IMPLEMENTED $5,910 $8,794 $1,905
37,807
kWh
$4,020
-
MMBtu
$(-15.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs