| Assessment Year | 1992 |
|---|---|
| Principal Product | HARDWOOD LUMBER |
| NAICS |
n/a
|
| SIC | 2431: Millwork |
| Sales Range | $10 M to 50M |
| # of Employees | 60 |
| Plant Area |
n/a
|
| Annual Production | 5,800
thousand feet
|
| Production Hrs. Annual | 4,426
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $72,610 | 1,010,258 |
kWh
|
$0.072 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $44,343 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|
| 01 | 3.6192: Use a less expensive method of waste removal | $30,000 | - | - | $30,000 | |
| 02 | 2.5123: Reduce fluid flow rates | $7,610 | $750 |
$7,610
114,889
kWh
|
- | |
| 03 | 2.3212: Optimize plant power factor | $3,370 | $6,000 |
$3,370
-
kWh
|
- | |
| 04 | 2.6212: Turn off equipment during breaks, reduce operating time | $1,990 | - |
$1,990
38,101
kWh
|
- | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $423 | $960 |
$480
7,034
kWh
|
$(-57.0) | |
| 06 | 2.6232: Install set-back timers | $350 | - |
$350
6,741
kWh
|
- | |
| 07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $340 | $300 |
$340
6,448
kWh
|
- | |
| 08 | 2.7111: Reduce illumination to minimum necessary levels | $260 | $510 |
$260
3,810
kWh
|
- | |
| TOTAL RECOMMENDED | $44,343 | $8,520 |
$14,400
177,023
kWh
|
$29,943 | ||
| TOTAL IMPLEMENTED | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs