ITAC Assessment: AM0138
ITAC logo
ITAC Assessment: AM0138
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1992
Principal Product SAND, GRAVEL, CONCRETE
NAICS
n/a
SIC 3273: Ready-Mixed Concrete
Sales Range $5
M
to 10
M
# of Employees 74
Plant Area
n/a
Annual Production 4,995
bbl
Production Hrs. Annual 3,540
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $342,722 3,311,841
kWh
Fuel Oil #4 $471,755 78,080
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $139,317 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $139,317

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.3192: Use fossil fuel powered generator during peak demand periods $132,770 $1,000,000 $214,200
2,529,308
kWh
$(-81,430.0)
-
MMBtu
02 2.3212: Optimize plant power factor $2,460 $640 $2,460
-
kWh
-
03 2.6232: Install set-back timers $940 - $940
26,084
kWh
-
04 2.4133: Use most efficient type of electric motors $3,147 $2,720 $3,147
34,877
kWh
-
TOTAL RECOMMENDED $139,317 $1,003,360 $220,747
2,590,269
kWh
$(-81,430.0)
-
MMBtu
TOTAL IMPLEMENTED $139,317 $1,003,360 $220,747
2,590,269
kWh
$(-81,430.0)
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs