Assessment Year 1991
Principal Product PRINTED NEWSPAPER ADVERTISEMENTS
NAICS
n/a
SIC 2752: Commercial Printing, Lithographic
Sales Range $10
M
to 50
M
# of Employees 170
Plant Area
n/a
Annual Production 21,108,000
lb
Production Hrs. Annual 4,896
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $212,190 3,788,980
kWh
Natural Gas $62,645 12,121
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $35,697 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.2414: Use waste heat from hot flue gases to preheat $24,600 $50,000 - $24,600
-
MMBtu
02 2.3212: Optimize plant power factor $8,786 $28,548 $8,786
-
kWh
-
03 2.3131: Reschedule plant operations or reduce load to avoid peaks $769 $2,520 $769
-
kWh
-
04 2.4231: Reduce the pressure of compressed air to the minimum required $490 - $490
7,620
kWh
-
05 2.3131: Reschedule plant operations or reduce load to avoid peaks $480 $200 $480
-
kWh
-
06 2.6232: Install set-back timers $472 - $472
8,206
kWh
-
07 2.7142: Utilize higher efficiency lamps and/or ballasts $100 $100 $100
1,172
kWh
-
TOTAL RECOMMENDED $35,697 $81,368 $11,097
16,998
kWh
$24,600
-
MMBtu
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs