ITAC Assessment: AM0094
ITAC logo
ITAC Assessment: AM0094
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1990
Principal Product MACHINE SHOP JOBS
NAICS
n/a
SIC 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 70
Plant Area
n/a
Annual Production 642
pieces
Production Hrs. Annual 4,832
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $223,672 3,633,060
kWh
Natural Gas $44,235 8,690
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $54,756 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $54,756

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4324: Replace hydraulic / pneumatic equipment with electric equipment $31,894 $22,000 $31,894
732,708
kWh
-
02 2.6232: Install set-back timers $8,700 $450 $8,700
195,487
kWh
-
03 2.7121: Utilize daylight whenever possible in lieu of artificial light $6,807 $7,920 $6,807
152,989
kWh
-
04 2.2136: Install / repair insulation on steam lines $2,870 $3,160 - $2,870
-
MMBtu
05 2.7111: Reduce illumination to minimum necessary levels $2,260 $675 $2,260
38,394
kWh
-
06 2.4312: Improve lubrication practices $670 - $670
15,240
kWh
-
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $715 $500 $715
16,120
kWh
-
08 2.1233: Analyze flue gas for proper air/fuel ratio $580 $270 - $580
-
MMBtu
09 2.6212: Turn off equipment during breaks, reduce operating time $260 - $260
5,862
kWh
-
TOTAL RECOMMENDED $54,756 $34,975 $51,306
1,156,800
kWh
$3,450
-
MMBtu
TOTAL IMPLEMENTED $54,756 $34,975 $51,306
1,156,800
kWh
$3,450
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs