Assessment Year | 1989 |
---|---|
Principal Product | ASPHALT ROOFING SHINGLES |
NAICS |
n/a
|
SIC | 2952: Asphalt Felts and Coatings |
Sales Range | $10 M to 50M |
# of Employees | 75 |
Plant Area |
n/a
|
Annual Production | 1,080,000
pieces
|
Production Hrs. Annual | 3,296
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $119,672 | 2,199,883 |
kWh
|
$0.054 |
Natural Gas | $200,898 | 60,541 |
MMBtu
|
$3.32 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $15,502 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $13,483 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $7,510 | - |
$7,510
-
kWh
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,170 | $3,600 |
$4,890
78,839
kWh
|
- | $280 | |
03 | 2.2437: Recover waste heat from equipment | $1,245 | $1,100 | - |
$1,245
-
MMBtu
|
- | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $703 | $500 |
$703
25,205
kWh
|
- | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $514 | - |
$514
18,464
kWh
|
- | - | |
06 | 2.4221: Install compressor air intakes in coolest locations | $260 | $300 |
$260
9,379
kWh
|
- | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $100 | $110 |
$100
1,758
kWh
|
- | - | |
TOTAL RECOMMENDED | $15,502 | $5,610 |
$13,977
133,645
kWh
|
$1,245
-
MMBtu
|
$280 | ||
TOTAL IMPLEMENTED | $13,483 | $4,210 |
$13,203
105,802
kWh
|
- | $280 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs