ITAC Assessment: AM0049
ITAC logo
ITAC Assessment: AM0049
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1988
Principal Product FABRICATED STEEL PRODUCTS
NAICS
n/a
SIC 3441: Fabricated Structural Metal
Sales Range $10
M
to 50
M
# of Employees 115
Plant Area
n/a
Annual Production 14,500
ton
Production Hrs. Annual 2,295
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $121,479 1,844,959
kWh
Natural Gas $28,018 5,939
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $10,065 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,819

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.2437: Recover waste heat from equipment $1,552 $2,400 - $1,552
-
MMBtu
-
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,299 $800 $3,299
108,734
kWh
- -
03 2.6212: Turn off equipment during breaks, reduce operating time $2,520 - $2,520
82,943
kWh
- -
04 2.6232: Install set-back timers $1,370 - $1,370
19,637
kWh
- -
05 3.4115: Recover and reuse cooling water $970 $2,700 $100
3,224
kWh
- $870
06 2.7142: Utilize higher efficiency lamps and/or ballasts $50 $60 $50
879
kWh
- -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $69 $5 $69
879
kWh
- -
08 2.4312: Improve lubrication practices $130 - $130
3,810
kWh
- -
09 2.4111: Utilize energy-efficient belts and other improved mechanisms $105 - $105
3,517
kWh
- -
TOTAL RECOMMENDED $10,065 $5,965 $7,643
223,623
kWh
$1,552
-
MMBtu
$870
TOTAL IMPLEMENTED $5,819 $800 $5,819
191,677
kWh
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs