ITAC Assessment: AM0045
ITAC logo
ITAC Assessment: AM0045
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1988
Principal Product CYLINDERS, PUMPS, MOTORS
NAICS
n/a
SIC 3593: Fluid Power Cylinders and Actuators
Sales Range $5
M
to 10
M
# of Employees 50
Plant Area
n/a
Annual Production 5,000
pieces
Production Hrs. Annual 2,660
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $25,630 352,579
kWh
Natural Gas $11,693 2,417
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $3,545 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,270

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.8121: Apply for tax-free status for energy purchases $1,838 $3,000 $1,838
-
kWh
- -
02 2.6218: Turn off equipment when not in use $645 $40 $45
1,465
kWh
$600
-
MMBtu
-
03 3.4154: Eliminate leaks in water lines and valves $400 $40 - - $400
04 2.2437: Recover waste heat from equipment $275 $550 - $275
-
MMBtu
-
05 2.7142: Utilize higher efficiency lamps and/or ballasts $48 $32 $48
879
kWh
- -
06 2.7261: Install timers and/or thermostats $194 $225 $60
2,052
kWh
$134
-
MMBtu
-
07 2.7142: Utilize higher efficiency lamps and/or ballasts $145 $336 $105
3,224
kWh
- $40
TOTAL RECOMMENDED $3,545 $4,223 $2,096
7,620
kWh
$1,009
-
MMBtu
$440
TOTAL IMPLEMENTED $3,270 $3,673 $2,096
7,620
kWh
$734
-
MMBtu
$440
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs