ITAC Assessment: AM0042
ITAC logo
ITAC Assessment: AM0042
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1988
Principal Product PREFABRICATED STEEL
NAICS
n/a
SIC 3448: Prefabricated Metal Buildings and Components
Sales Range $10
M
to 50
M
# of Employees 148
Plant Area
n/a
Annual Production 15,300
ton
Production Hrs. Annual 5,200
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $74,160 1,258,499
kWh
Natural Gas $13,624 3,352
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $9,491 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,001

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,470 $150 $3,470
83,822
kWh
-
02 2.7245: Use direct air supply to exhaust hoods $1,935 $10,000 - $1,935
-
MMBtu
03 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available $1,325 $1,200 $1,325
31,946
kWh
-
04 2.2437: Recover waste heat from equipment $1,145 $1,000 - $1,145
-
MMBtu
05 2.6212: Turn off equipment during breaks, reduce operating time $520 $520 $520
12,603
kWh
-
06 2.6218: Turn off equipment when not in use $438 $150 - $438
-
MMBtu
07 2.7261: Install timers and/or thermostats $400 $1,000 $260
3,517
kWh
$140
-
MMBtu
08 2.7142: Utilize higher efficiency lamps and/or ballasts $76 $220 $76
1,172
kWh
-
09 2.4312: Improve lubrication practices $182 - $182
4,396
kWh
-
TOTAL RECOMMENDED $9,491 $14,240 $5,833
137,456
kWh
$3,658
-
MMBtu
TOTAL IMPLEMENTED $6,001 $10,890 $4,066
97,597
kWh
$1,935
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs