| Assessment Year | 1988 |
|---|---|
| Principal Product | INSECTICIDES, HERBICIDES |
| NAICS |
n/a
|
| SIC | 2879: Pesticides and Agricultural Chemicals, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 31 |
| Plant Area |
n/a
|
| Annual Production | 1,540
Tgal
|
| Production Hrs. Annual | 8,736
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $119,053 | 1,936,401 |
kWh
|
$0.061 |
| Natural Gas | $20,200 | 5,575 |
MMBtu
|
$3.62 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $9,297 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $2,804 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7492: Use proper thickness of insulation on building envelope | $3,735 | $6,790 | - |
$3,735
-
MMBtu
|
|
| 02 | 2.8112: Combine utility meters | $1,450 | $2,000 | - |
$1,450
-
MMBtu
|
|
| 03 | 2.2136: Install / repair insulation on steam lines | $115 | $94 | - |
$115
-
MMBtu
|
|
| 04 | 2.2122: Install / repair insulation on condensate lines | $1,193 | $504 | - |
$1,193
-
MMBtu
|
|
| 05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,096 | - |
$1,096
24,912
kWh
|
- | |
| 06 | 2.4312: Improve lubrication practices | $640 | - |
$640
14,654
kWh
|
- | |
| 07 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $671 | $2,325 |
$671
15,240
kWh
|
- | |
| 08 | 2.6232: Install set-back timers | $325 | - |
$325
5,275
kWh
|
- | |
| 09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $72 | $162 |
$72
879
kWh
|
- | |
| TOTAL RECOMMENDED | $9,297 | $11,875 |
$2,804
60,960
kWh
|
$6,493
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $2,804 | $2,487 |
$2,804
60,960
kWh
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs