Assessment Year | 1987 |
---|---|
Principal Product | MISCELLANEOUS PLASTICS |
NAICS |
n/a
|
SIC | 2673: Plastics, Foil, and Coated Paper Bags |
Sales Range | $10 M to 50M |
# of Employees | 70 |
Plant Area |
n/a
|
Annual Production | 31,000,000
lb
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $508,387 | 12,702,521 |
kWh
|
$0.040 |
Natural Gas | $21,123 | 6,103 |
MMBtu
|
$3.46 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $40,545 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $29,836 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.3511: Use plant owned transformers or lease transformers | $16,728 | $40,345 |
$16,728
-
kWh
|
- | |
02 | 2.2511: Insulate bare equipment | $10,709 | $5,600 |
$10,709
362,837
kWh
|
- | |
03 | 2.4312: Improve lubrication practices | $4,505 | - |
$4,505
117,526
kWh
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,812 | $3,227 |
$2,812
71,512
kWh
|
- | |
05 | 2.2437: Recover waste heat from equipment | $2,870 | $300 | - |
$2,870
-
MMBtu
|
|
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,677 | $2,089 |
$1,677
42,497
kWh
|
- | |
07 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $540 | - |
$540
18,171
kWh
|
- | |
08 | 2.8114: Change rate schedules or other changes in utility service | $446 | $80 |
$446
4,982
kWh
|
- | |
09 | 2.6232: Install set-back timers | $258 | - |
$258
4,396
kWh
|
- | |
TOTAL RECOMMENDED | $40,545 | $51,641 |
$37,675
621,921
kWh
|
$2,870
-
MMBtu
|
||
TOTAL IMPLEMENTED | $29,836 | $46,041 |
$26,966
259,084
kWh
|
$2,870
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs