ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC 2+ Digits Required
3+ Characters Required for Products

26

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $2,370k 791k
MMBtu
$5.52
- Electrical $207k 6,905k
kWh
$0.040
- Natural Gas $939k 274k
MMBtu
$4.79

187

Recommendations

7.2

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $113k 25k
MMBtu
3.2%
- Electrical $54k 2,442k
kWh
35.4%
- Natural Gas $110k -
MMBtu
-
Waste $0.7k
Productivity/Other $7.6k
TOTAL $121k
*May be negative reflecting an increased cost component required to save energy and costs overall

24

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $2,554k 856k
MMBtu
$5.28
- Electrical $220k 7,374k
kWh
$0.040
- Natural Gas $1,013k 296k
MMBtu
$4.66

93

Implemented Recommendations

3.9

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $45k 1.5k
MMBtu
0.2%
- Electrical $6.4k 142k
kWh
1.9%
- Natural Gas $111k -
MMBtu
-
Waste $0.6k
Productivity/Other $4.6k
TOTAL $50k