ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC 2+ Digits Required
3+ Characters Required for Products

239

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $528k 106k
MMBtu
$5.65
- Electrical $252k 6,517k
kWh
$0.10
- Natural Gas $157k 36k
MMBtu
$4.75

1,718

Recommendations

7.2

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $35k 4.2k
MMBtu
3.9%
- Electrical $22k 408k
kWh
6.3%
- Natural Gas $7.9k -
MMBtu
-
Waste $5.2k
Productivity/Other $39k
TOTAL $79k
*May be negative reflecting an increased cost component required to save energy and costs overall

231

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $515k 107k
MMBtu
$5.46
- Electrical $251k 6,588k
kWh
$0.10
- Natural Gas $150k 35k
MMBtu
$4.63

835

Implemented Recommendations

3.6

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $12k 1.6k
MMBtu
1.5%
- Electrical $6.0k 159k
kWh
2.4%
- Natural Gas $3.8k -
MMBtu
-
Waste $3.4k
Productivity/Other $13k
TOTAL $29k
*May be negative reflecting an increased cost component required to save energy and costs overall