ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC 2+ Digits Required
3+ Characters Required for Products

129

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $1,118k 617k
MMBtu
$9.37
- Electrical $669k 8,943k
kWh
$0.20
- Natural Gas $266k 510k
MMBtu
$7.21

1,079

Recommendations

8.4

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $182k 13k
MMBtu
2.1%
- Electrical $112k 1,288k
kWh
14.4%
- Natural Gas $44k -
MMBtu
-
Waste $2.6k
Productivity/Other $9.7k
TOTAL $195k
*May be negative reflecting an increased cost component required to save energy and costs overall

122

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $1,111k 645k
MMBtu
$9.32
- Electrical $668k 8,922k
kWh
$0.21
- Natural Gas $271k 538k
MMBtu
$7.16

454

Implemented Recommendations

3.7

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $79k 5.0k
MMBtu
0.8%
- Electrical $47k 488k
kWh
5.5%
- Natural Gas $25k -
MMBtu
-
Waste $1.4k
Productivity/Other $3.7k
TOTAL $84k
*May be negative reflecting an increased cost component required to save energy and costs overall