ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC 2+ Digits Required
3+ Characters Required for Products

670

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $385k 83k
MMBtu
$6.19
- Electrical $194k 4,616k
kWh
$0.048
- Natural Gas $114k 29k
MMBtu
$4.82

4,888

Recommendations

7.3

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $33k 4.7k
MMBtu
5.7%
- Electrical $21k 460k
kWh
10.0%
- Natural Gas $7.4k -
MMBtu
-
Waste $2.3k
Productivity/Other $36k
TOTAL $71k
*May be negative reflecting an increased cost component required to save energy and costs overall

643

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $388k 85k
MMBtu
$6.02
- Electrical $197k 4,720k
kWh
$0.048
- Natural Gas $116k 30k
MMBtu
$4.73

2,634

Implemented Recommendations

4.1

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $14k 1.6k
MMBtu
1.9%
- Electrical $7.6k 160k
kWh
3.4%
- Natural Gas $3.8k -
MMBtu
-
Waste $0.9k
Productivity/Other $13k
TOTAL $27k
*May be negative reflecting an increased cost component required to save energy and costs overall