ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC 2+ Digits Required
3+ Characters Required for Products

578

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $602k 120k
MMBtu
$8.64
- Electrical $374k 6,613k
kWh
$0.086
- Natural Gas $86k 36k
MMBtu
$3.71

4,412

Recommendations

7.6

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $75k 12k
MMBtu
9.8%
- Electrical $66k 1,143k
kWh
17.3%
- Natural Gas ($-8.8)k -
MMBtu
-
Waste $2.6k
Productivity/Other $90k
TOTAL $168k
*May be negative reflecting an increased cost component required to save energy and costs overall

548

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $592k 123k
MMBtu
$8.41
- Electrical $372k 6,682k
kWh
$0.086
- Natural Gas $87k 37k
MMBtu
$3.60

1,673

Implemented Recommendations

3.1

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $25k 3.5k
MMBtu
2.8%
- Electrical $21k 339k
kWh
5.1%
- Natural Gas ($-0.2)k -
MMBtu
-
Waste $1.0k
Productivity/Other $29k
TOTAL $55k
*May be negative reflecting an increased cost component required to save energy and costs overall