The ITAC Statistics page displays the average assessment results for the selected criteria.
9
Matching Assessments
| Initial Plant Size Averages | Costs | Usage | Unit Cost | |
|---|---|---|---|---|
| All Energy | $413k | 28k |
MMBtu
|
$11.84 |
| - Electrical | $110k | 1,674k |
kWh
|
$0.092 |
| - Natural Gas | $5.1k | 0.8k |
MMBtu
|
$4.60 |
49
Recommendations
5.4
Recommendations Per Assessment
| Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
|---|---|---|---|---|
| All Energy | $155k | 0.8k |
MMBtu
|
2.9% |
| - Electrical | $10k | 79k |
kWh
|
4.7% |
| - Natural Gas | $0.4k | - |
MMBtu
|
- |
| Waste | $0.3k | |||
| Productivity/Other | $1.2k | |||
| TOTAL | $156k | |||
| *May be negative reflecting an increased cost component required to save energy and costs overall | ||||
9
with Implementation Data
| Initial Plant Size Averages | Costs | Usage | Unit Cost | |
|---|---|---|---|---|
| All Energy | $413k | 28k |
MMBtu
|
$11.84 |
| - Electrical | $110k | 1,674k |
kWh
|
$0.092 |
| - Natural Gas | $5.1k | 0.8k |
MMBtu
|
$4.60 |
20
Implemented Recommendations
2.2
Implemented Per Assessment
| Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
|---|---|---|---|---|
| All Energy | $14k | 0.8k |
MMBtu
|
2.9% |
| - Electrical | $4.7k | 78k |
kWh
|
4.7% |
| - Natural Gas | $0.3k | - |
MMBtu
|
- |
| Waste | $0.3k | |||
| Productivity/Other | ($-0.4)k | |||
| TOTAL | $14k | |||
| *May be negative reflecting an increased cost component required to save energy and costs overall | ||||