The ITAC Statistics page displays the average assessment results for the selected criteria.
8
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $101k | 10k |
MMBtu
|
$11.14 |
- Electrical | $75k | 915k |
kWh
|
$0.097 |
- Natural Gas | $5.7k | 0.9k |
MMBtu
|
$5.18 |
35
Recommendations
4.4
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $15k | 1.3k |
MMBtu
|
12.6% |
- Electrical | $14k | 126k |
kWh
|
13.8% |
- Natural Gas | $0.5k | - |
MMBtu
|
- |
Waste | $0.4k | |||
Productivity/Other | $0.0k | |||
TOTAL | $15k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
5
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $126k | 13k |
MMBtu
|
$11.37 |
- Electrical | $89k | 1,201k |
kWh
|
$0.082 |
- Natural Gas | $5.5k | 0.7k |
MMBtu
|
$5.01 |
15
Implemented Recommendations
3.0
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $3.2k | 0.2k |
MMBtu
|
1.3% |
- Electrical | $1.7k | 17k |
kWh
|
1.4% |
- Natural Gas | $0.6k | - |
MMBtu
|
- |
Waste | $0.6k | |||
Productivity/Other | $0.0k | |||
TOTAL | $3.7k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |