The ITAC Statistics page displays the average assessment results for the selected criteria.
21
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $470k | 44k |
MMBtu
|
$10.96 |
- Electrical | $275k | 3,507k |
kWh
|
$0.085 |
- Natural Gas | $45k | 6.0k |
MMBtu
|
$7.61 |
124
Recommendations
5.9
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $97k | 8.5k |
MMBtu
|
19.2% |
- Electrical | $66k | 831k |
kWh
|
23.7% |
- Natural Gas | $6.2k | - |
MMBtu
|
- |
Waste | $0.8k | |||
Productivity/Other | $23k | |||
TOTAL | $121k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
19
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $472k | 44k |
MMBtu
|
$11.07 |
- Electrical | $277k | 3,384k |
kWh
|
$0.087 |
- Natural Gas | $47k | 6.3k |
MMBtu
|
$7.58 |
44
Implemented Recommendations
2.3
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $18k | 1.5k |
MMBtu
|
3.5% |
- Electrical | $11k | 150k |
kWh
|
4.4% |
- Natural Gas | $0.4k | - |
MMBtu
|
- |
Waste | - | |||
Productivity/Other | $26k | |||
TOTAL | $44k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |