The ITAC Statistics page displays the average assessment results for the selected criteria.
5
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $62k | 6.5k |
MMBtu
|
$9.49 |
- Electrical | $49k | 605k |
kWh
|
$0.083 |
- Natural Gas | $3.1k | 0.3k |
MMBtu
|
$2.14 |
18
Recommendations
3.6
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $18k | 2.2k |
MMBtu
|
34.3% |
- Electrical | $17k | 217k |
kWh
|
35.9% |
- Natural Gas | - | - |
MMBtu
|
- |
Waste | - | |||
Productivity/Other | - | |||
TOTAL | $18k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
2
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $61k | 6.2k |
MMBtu
|
$9.79 |
- Electrical | $46k | 536k |
kWh
|
$0.087 |
- Natural Gas | $7.8k | 0.7k |
MMBtu
|
$5.36 |
6
Implemented Recommendations
3.0
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $13k | 1.5k |
MMBtu
|
23.7% |
- Electrical | $12k | 144k |
kWh
|
26.9% |
- Natural Gas | - | - |
MMBtu
|
- |
Waste | - | |||
Productivity/Other | - | |||
TOTAL | $13k | |||