The ITAC Statistics page displays the average assessment results for the selected criteria.
18
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $218k | 26k |
MMBtu
|
$9.82 |
- Electrical | $138k | 2,115k |
kWh
|
$0.085 |
- Natural Gas | $20k | 3.4k |
MMBtu
|
$3.52 |
104
Recommendations
5.8
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $27k | 2.8k |
MMBtu
|
10.9% |
- Electrical | $20k | 276k |
kWh
|
13.0% |
- Natural Gas | $2.1k | - |
MMBtu
|
- |
Waste | - | |||
Productivity/Other | $3.1k | |||
TOTAL | $30k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
16
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $225k | 27k |
MMBtu
|
$9.79 |
- Electrical | $141k | 2,178k |
kWh
|
$0.084 |
- Natural Gas | $22k | 3.8k |
MMBtu
|
$3.54 |
57
Implemented Recommendations
3.6
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $14k | 1.5k |
MMBtu
|
5.4% |
- Electrical | $9.7k | 142k |
kWh
|
6.5% |
- Natural Gas | $2.3k | - |
MMBtu
|
- |
Waste | - | |||
Productivity/Other | $0.2k | |||
TOTAL | $14k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |