ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Schools and educational services, not elsewhere
3+ Characters Required for Products

2

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $86k 8.4k
MMBtu
$10.08
- Electrical $41k 322k
kWh
$0.12
- Natural Gas $38k 5.1k
MMBtu
$7.39

13

Recommendations

6.5

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $13k 0.8k
MMBtu
9.9%
- Electrical $11k 82k
kWh
25.3%
- Natural Gas $2.3k -
MMBtu
-
Waste $0.7k
Productivity/Other $3.6k
TOTAL $17k
*May be negative reflecting an increased cost component required to save energy and costs overall

2

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $86k 8.4k
MMBtu
$10.08
- Electrical $41k 322k
kWh
$0.12
- Natural Gas $38k 5.1k
MMBtu
$7.39

3

Implemented Recommendations

1.5

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $2.3k 0.2k
MMBtu
2.7%
- Electrical $1.9k 22k
kWh
7.0%
- Natural Gas $0.3k -
MMBtu
-
Waste -
Productivity/Other $0.4k
TOTAL $2.6k
*May be negative reflecting an increased cost component required to save energy and costs overall