The ITAC Statistics page displays the average assessment results for the selected criteria.
97
Matching Assessments
| Initial Plant Size Averages | Costs | Usage | Unit Cost | |
|---|---|---|---|---|
| All Energy | $137k | 13k |
MMBtu
|
$11.86 |
| - Electrical | $88k | 1,019k |
kWh
|
$0.088 |
| - Natural Gas | $16k | 2.0k |
MMBtu
|
$6.65 |
505
Recommendations
5.2
Recommendations Per Assessment
| Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
|---|---|---|---|---|
| All Energy | $44k | 4.0k |
MMBtu
|
31.6% |
| - Electrical | $34k | 386k |
kWh
|
37.9% |
| - Natural Gas | $1.4k | - |
MMBtu
|
- |
| Waste | $1.2k | |||
| Productivity/Other | $1.3k | |||
| TOTAL | $46k | |||
| *May be negative reflecting an increased cost component required to save energy and costs overall | ||||
52
with Implementation Data
| Initial Plant Size Averages | Costs | Usage | Unit Cost | |
|---|---|---|---|---|
| All Energy | $158k | 16k |
MMBtu
|
$11.48 |
| - Electrical | $113k | 1,236k |
kWh
|
$0.10 |
| - Natural Gas | $21k | 2.8k |
MMBtu
|
$4.35 |
141
Implemented Recommendations
2.7
Implemented Per Assessment
| Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
|---|---|---|---|---|
| All Energy | $17k | 1.6k |
MMBtu
|
10.3% |
| - Electrical | $14k | 156k |
kWh
|
12.6% |
| - Natural Gas | $0.7k | - |
MMBtu
|
- |
| Waste | $0.0k | |||
| Productivity/Other | $0.2k | |||
| TOTAL | $17k | |||
| *May be negative reflecting an increased cost component required to save energy and costs overall | ||||