The ITAC Statistics page displays the average assessment results for the selected criteria.
6
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $414k | 51k |
MMBtu
|
$8.93 |
- Electrical | $220k | 3,640k |
kWh
|
$0.066 |
- Natural Gas | $103k | 14k |
MMBtu
|
$6.68 |
43
Recommendations
7.2
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $51k | 4.4k |
MMBtu
|
8.6% |
- Electrical | $26k | 427k |
kWh
|
11.7% |
- Natural Gas | $19k | - |
MMBtu
|
- |
Waste | $0.8k | |||
Productivity/Other | $0.4k | |||
TOTAL | $52k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
6
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $414k | 51k |
MMBtu
|
$8.93 |
- Electrical | $220k | 3,640k |
kWh
|
$0.066 |
- Natural Gas | $103k | 14k |
MMBtu
|
$6.68 |
18
Implemented Recommendations
3.0
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $18k | 1.4k |
MMBtu
|
2.8% |
- Electrical | $8.0k | 137k |
kWh
|
3.8% |
- Natural Gas | $8.4k | - |
MMBtu
|
- |
Waste | $0.8k | |||
Productivity/Other | $0.3k | |||
TOTAL | $19k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |