The ITAC Statistics page displays the average assessment results for the selected criteria.
9
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $460k | 60k |
MMBtu
|
$8.74 |
- Electrical | $219k | 4,879k |
kWh
|
$0.058 |
- Natural Gas | $72k | 9.6k |
MMBtu
|
$6.47 |
68
Recommendations
7.6
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $41k | 4.4k |
MMBtu
|
7.3% |
- Electrical | $23k | 427k |
kWh
|
8.8% |
- Natural Gas | $13k | - |
MMBtu
|
- |
Waste | $0.5k | |||
Productivity/Other | $0.3k | |||
TOTAL | $42k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
7
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $553k | 72k |
MMBtu
|
$8.64 |
- Electrical | $264k | 5,907k |
kWh
|
$0.060 |
- Natural Gas | $88k | 12k |
MMBtu
|
$5.73 |
19
Implemented Recommendations
2.7
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $17k | 1.8k |
MMBtu
|
2.4% |
- Electrical | $8.3k | 171k |
kWh
|
2.9% |
- Natural Gas | $7.2k | - |
MMBtu
|
- |
Waste | $0.7k | |||
Productivity/Other | $0.2k | |||
TOTAL | $18k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |