The ITAC Statistics page displays the average assessment results for the selected criteria.
13
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $244k | 21k |
MMBtu
|
$10.89 |
- Electrical | $153k | 1,755k |
kWh
|
$0.088 |
- Natural Gas | $22k | 3.0k |
MMBtu
|
$5.21 |
83
Recommendations
6.4
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $97k | 8.3k |
MMBtu
|
39.4% |
- Electrical | $68k | 807k |
kWh
|
46.0% |
- Natural Gas | $2.8k | - |
MMBtu
|
- |
Waste | $0.3k | |||
Productivity/Other | $9.1k | |||
TOTAL | $107k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
9
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $133k | 14k |
MMBtu
|
$10.31 |
- Electrical | $84k | 974k |
kWh
|
$0.090 |
- Natural Gas | $25k | 3.7k |
MMBtu
|
$5.52 |
26
Implemented Recommendations
2.9
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $13k | 1.1k |
MMBtu
|
7.8% |
- Electrical | $9.6k | 104k |
kWh
|
10.6% |
- Natural Gas | $0.9k | - |
MMBtu
|
- |
Waste | $0.0k | |||
Productivity/Other | $3.6k | |||
TOTAL | $16k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |